Control Centre Operations |
| TRANSMISSION / OASIS MESSAGES | |
| |
| |
| | 624 | Posted: | Mar 11, 2010 11:40 | Posted by: |
| | NSPI TransmissionSystemOp |
| | Transmission Normal |
| | 67N-T81 is back in service. No restrictions. |
| | ________________________________________________________________________________ |
| | 623 | Posted: | Mar 10, 2010 17:48 | Posted by: |
| | NSPI EnergySystemOperator |
| | 120H SVC |
| | 120H-SVC is now back in service |
| | ________________________________________________________________________________ |
| | 622 | Posted: | Mar 09, 2010 08:40 | Posted by: |
| | NSPI TransmissionSystemOp |
| | Transmission Outage |
| | 120H-SVC SVC Maintenance at 120H terminal. No Restrictions. |
| | ________________________________________________________________________________ |
| | 621 | Posted: | Mar 08, 2010 19:01 | Posted by: |
| | NSPI TransmissionSystemOp |
| | Transmission Normal |
| | L-8001 sky wire repairs completed at 18:55. Restrictions lifted. |
| | ________________________________________________________________________________ |
| | 620 | Posted: | Mar 08, 2010 10:39 | Posted by: |
| | NSPI TransmissionSystemOp |
| | Curtailment |
| | L-8001 Reducing NS Import Limit to 80MW'S. Do to broken sky wire and potential for system seperation. |
| | ________________________________________________________________________________ |
| | 619 | Posted: | Mar 08, 2010 09:00 | Posted by: |
| | NSPI TransmissionSystemOp |
| | Transmission Outage |
| | 67N-T81 Replace lightning arrestors on 67N-T81. No Restrictions. |
| | ________________________________________________________________________________ |
| | 616 | Posted: | Feb 22, 2010 11:28 | Posted by: |
| | Alison Gillan |
| | UARB Approves Revised GIP |
| | On February 10, 2010 the NSUARB approved NSPI's filing for a revised Generator Interconnection Procedure (GIP) with an effective date of February 22, 2010. All revised GIP documents and details can be found at: http://oasis.nspower.ca/en/home/oasis/revisedgenerationinterconnectionprocedures.aspx |
| | ________________________________________________________________________________ |
| | 611 | Posted: | Feb 10, 2010 10:38 | Posted by: |
| | Alison Gillan |
| | Employee transfer |
| | Effective March 1, 2010 Francis DeBay will assume the role of System Control Superintendent, Energy and Transmission, within NSPSO. Previously Francis was Team Leader on the Marketing Desk with Fuels, Energy and Risk Management at NSPI. |
| | ________________________________________________________________________________ |
| | Last Updated: Mar 11, 2010 13:04 |