Interruptions de la catégorie 1 et de la catégorie 2
| Numéro d'interruption | Statut | Heure de début | Heure d'arrêt | But |
| 7077 | APPROUVÉ | 2 mai, 2012 AD | 18 mai, 2012 AD | Adjust the MPS TTC for element out of service |
| 6806 | APPROUVÉ | 12 mai, 2012 AD | 26 mai, 2012 AD | annual outage |
| 7045 | APPROUVÉ | 14 mai, 2012 AD | 18 mai, 2012 AD | Relay Dept.; perform NPCC DC Logic Maintenance on Breaker Failure, L1108, L1142, L1143, L1157, L1159, L1160, and L1190 Protections.
We will need to trip every 138KV breaker O-A-A-T. (ME1-6, ME1-7, ME1-8, ME1-9, ME1-10, ME1-11, ME1-12, ME1-13, ME1-14, and ME1-15) We would prefer to trip the breakers at any time throughout the week and can accomodate any system conditions (i.e. Holdoffs) on a day-to-day basis. |
| 6923 | APPROUVÉ | 14 mai, 2012 AD | 1 juin, 2012 AD | require 345 yard RTU offline during LICOM replacement, also require 138 yard breaker failure on CS1201-01 out of service during this time as well, as there will be no communications during the equipment replacement
will require L1201 tone control handles turned to off position at Bathurst |
| 6924 | APPROUVÉ | 14 mai, 2012 AD | 1 juin, 2012 AD | require 345 yard RTU offline during LICOM replacement, also require 138 yard breaker failure on CS1201-01 out of service during this time, as there will be no communications during the equipment replacement
will require L1201 tone control handles turned to off position at Bathurst |
| 7069 | APPROUVÉ | 15 mai, 2012 AD | 17 mai, 2012 AD | Trip breakers K3-5 and K3-6 from the breaker failure Protection since this was not done when B.F. maintenance was completed; since L3001 was to have a planned outage. Need to operate disconnects 6B32, 6B36, 5B36 and 5B35 since the push button stations for the motor operators are to be changed out during the Outage. 6B32 and 5B35 will be operated during the return switching. Reference TLM Request #6356. |
| 6356 | APPROUVÉ | 15 mai, 2012 AD | 17 mai, 2012 AD | TLM; L3001 Outage required for switch maintenance, and removal of old Telecom. L3001 Carrier equipment (Wavetraps and Coupling Cap.'s) from the Line. |
| 6895 | ANNULÉ | 21 mai, 2012 AD | 22 mai, 2012 AD | hold off Bus 38 to service switches 8B34 and 8B36 (with breaker CO3-8 open), second day is rain day |
| 7076 | APPROUVÉ | 24 mai, 2012 AD | 5 juin, 2012 AD | HVEM's; Permit required to perform maintenance on SST transformer, syl-gard P3-6 and P3-9 grading caps., repair oil leak P3-9 CT, and syl-gard Bus 32 CVT. TLM will be applying for a separate Permit, same Protection points. The second week of the SST outage (approx. May 28 ), Bus 32 can be put back in service and an In-Plant Permit can be in place using SST1D-345. |
| 6011 | APPROUVÉ | 28 mai, 2012 AD | 1 juin, 2012 AD | work permit to replace insulators on L3017/L3019, TLM wants to service switch 3017-01D during the switching at the start of the job |
| 6012 | ANNULÉ | 28 mai, 2012 AD | 1 juin, 2012 AD | work permit to replace insulators on L3017/L3019 |
| 6424 | APPROUVÉ | 28 mai, 2012 AD | 1 juin, 2012 AD | work permit to replace insulators on L3017/L3019 (previously requested as #6012, but was set as a forced outage rather than planned outage) |
| 6582 | APPROUVÉ | 28 mai, 2012 AD | 1 juin, 2012 AD | HVEM's; permit required to perform T3 bushing testing, R1 and R2 six year maintenance, and SAR1 and SAR2 six year maintenance. |
| 6594 | ANNULÉ | 28 mai, 2012 AD | 1 juin, 2012 AD | HVEM's; permit required to perform the six year maintenance on breaker CO3-8, and also apply syl-gard to the breaker. |
| 6712 | ÉVALUATION | 28 mai, 2012 AD | 8 juin, 2012 AD | HVEM's; permit required to perform the six year overhaul on TU2 transformer, and Doble test the U2 PT. |
| 7120 | APPROUVÉ | 28 mai, 2012 AD | 30 mai, 2012 AD | Relay Dept,; perform NPCC DC Logic testing on L3017. SA3-1 and SA3-2 Breaker trips OAAT on all 3 days, during planned L3017 outage. |
| 7142 | ÉVALUATION | 29 mai, 2012 AD | 29 mai, 2012 AD | work permit to service switches U2-D, U2-G and U2-GB (Hydro planning contacted about the work) |
| 7086 | PAS APPROUVÉ | 1 juin, 2012 AD | 3 juin, 2012 AD | Telecom and a contractor will be replacing/reterminating the fiber optic cables at the Turgeon Road Sub (Belledune Sub), this will affect the RTU communications to ECC from the Sub. Alyre has discussed the work with the Plant and has planned this for the weekend so if there is a loss of station service there will be no work going on in the Plant. |
| 6542 | ÉVALUATION | 4 juin, 2012 AD | 8 juin, 2012 AD | HVEM's; Permit required to perform the 12 year overhaul on breaker 1126-1. |
| 6376 | PAS APPROUVÉ | 4 juin, 2012 AD | 6 juin, 2012 AD | HVEM's; Permit required to apply syl-gard to L3009 CVT's at Lepreau. |
| 7112 | ANNULÉ | 6 juin, 2012 AD | 8 juin, 2012 AD | Trip Breakers K3-2 and K3-3 from L3011 since we couldn't trip them when the DC logic was done due to system conditions. Breaker Trips on Thurday, June 7. May be impacted by the planned L2130 Outage June 4-7. |
| 7023 | PAS APPROUVÉ | 9 juin, 2012 AD | 12 juin, 2012 AD | work permit to remove 'temporary' bypass between L3008 and L3018, and service switches BE3008D and BE3018D if not serviced prior to this outage, Relay will have a separate outage request for their work |
| 6945 | ANNULÉ | 11 juin, 2012 AD | 24 juin, 2012 AD | HVEM's; Permit required to perform maintenance on SST transformer, syl-gard P3-6 and P3-9 grading caps., repair oil leak P3-9 CT, and syl-gard Bus 32 CVT. TLM will be applying for a separate Permit, same Protection points. The second week of the SST outage (approx. June 18-24), Bus 32 can be put back in service and an In-Plant Permit can be in place using SST1D-345. |
| 6713 | PAS APPROUVÉ | 11 juin, 2012 AD | 22 juin, 2012 AD | HVEM's; permit required to perform the six year overhaul on transformer TU6. |
| 4728 | PAS APPROUVÉ | 11 juin, 2012 AD | 15 juin, 2012 AD | HVEM's; perform 15 year overhaul on breaker ETC1. |
| 6642 | ÉVALUATION | 13 juin, 2012 AD | 14 juin, 2012 AD | HVEM's; permit required to install station class lightning arrestors on L3006 and Doble test the L3006 CVT's. |
| 6643 | ÉVALUATION | 13 juin, 2012 AD | 14 juin, 2012 AD | HVEM's; permit required to install station class lightning arrestors on L3006. |
| 6644 | ÉVALUATION | 13 juin, 2012 AD | 14 juin, 2012 AD | work permit to install line arrestors on L3006 at Salisbury and Memramcook and repair a hotspot on switch SA3-2D2 |
| 7089 | PAS APPROUVÉ | 13 juin, 2012 AD | 14 juin, 2012 AD | work permit to repair/replace counterbalance on SST1D-345, and repair broken piece on switch 7D2 (if required) |
| 6858 | ANNULÉ | 15 juin, 2012 AD | 17 juin, 2012 AD | Remove line section to allow for footing installation at Orrington |
| 6873 | ÉVALUATION | 15 juin, 2012 AD | 19 juin, 2012 AD | MPRP related work at Orrington |
| 7042 | ANNULÉ | 18 juin, 2012 AD | 21 juin, 2012 AD | HVEM's; permit required to replace one leaking L1133 PT at Keswick, during the planned L1133 Outage for the Protection Upgrade / RELAY. (#6969) |
| 7008 | PAS APPROUVÉ | 18 juin, 2012 AD | 21 juin, 2012 AD | HVEM's; permit required to repair leaking L1133 PT at Keswick. To be done during Relay's planned 4 day L1133 outage (Prot. upgrade). |
| 6969 | PAS APPROUVÉ | 18 juin, 2012 AD | 21 juin, 2012 AD | Relay Dept.; Permit required to install four additional L1133 A&B Protection Tones (one Permissive and one Direct Trip for each A&B) between Mactaquac and Keswick. |
| 4715 | PAS APPROUVÉ | 18 juin, 2012 AD | 22 juin, 2012 AD | HVEM's; perform 15 year overhaul on breaker K3-4. |
| 4721 | ANNULÉ | 18 juin, 2012 AD | 21 juin, 2012 AD | HVEM's; replace Bathurst L2131 PT's (3), Capital Job. |
| 6977 | PAS APPROUVÉ | 19 juin, 2012 AD | 29 juin, 2012 AD | HVEM's; Permit required to perform maintenance on T312, 37-02, TSSA, and Doble test the Bus PT's and L0037 PT. TLM will be working under their own Permit. FDE jumpers to be removed under H.O. |
| 6600 | ANNULÉ | 19 juin, 2012 AD | 29 juin, 2012 AD | HVEM's; Permit required to perform the following work.... breaker T312 six year maintenance, TSSA overhaul and change oil, 4331-S001 maintenance, breaker 37-02 six year maintenance, doble test L0037 PT, Doble test U2 Bus PT's. TLM will also be applying for their own Permit for switch maintenance. Work to be done during Generation's planned Unit #2 2012 Outage. Require Radial to be on NB for this work. |
| 6981 | PAS APPROUVÉ | 19 juin, 2012 AD | 22 juin, 2012 AD | work permit to service switches T314, TS37-22 (during switching) and T312D, repairing condition abnormal # 605 on T314 during the outage |
| 7143 | PAS APPROUVÉ | 19 juin, 2012 AD | 19 juin, 2012 AD | work permit to service switches U6-D, U6-G and U6-GB (Hydro planning contacted about the work) |
| 7014 | ÉVALUATION | 20 juin, 2012 AD | 23 juin, 2012 AD | HVEM's; permit required to replace the L3016 CVT and Doble test the metering CT's and PT's at Lepreau. Reference TLM Outage Request #6355. |
| 7080 | ANNULÉ | 20 juin, 2012 AD | 23 juin, 2012 AD | HVEM's; permit required to replace the Lepreau L3016 CVT, during the planned L3016 Outage. Reference TLM Request #6355. |
| 7081 | ÉVALUATION | 20 juin, 2012 AD | 23 juin, 2012 AD | Relay Dept.; permit required to replace / commission the L3016 CVT, during the planned L3016 Outage. |
| 6940 | PAS APPROUVÉ | 20 juin, 2012 AD | 3 juillet, 2012 AD | HVEM's; Permit required to repair fans on T1, replace heaters on IR1-3, and Doble test L1212X PT's (Sub#2). Another Permit will be applied for, so Permashell can paint the steel structures on the T1 side of Sub#2. Same Protection points. |
| 6355 | ÉVALUATION | 20 juin, 2012 AD | 23 juin, 2012 AD | TLM; L3016 Outage required to perform switch maintenance, marker balls installation, Line structure inspections, CVT replacement. |
| 4606 | PAS APPROUVÉ | 25 juin, 2012 AD | 29 juin, 2012 AD | HVEM's; perform six year overhaul on T1 transformer, doble T1 PT, and six year maintenance on breakers SA2145, SA1-5 and SA1-6. |
| 6953 | PAS APPROUVÉ | 25 juin, 2012 AD | 11 juillet, 2012 AD | HVEM's; Permit required to perform UT's overhauls, UST overhaul and leak repair, syl-gard U1 CVT, syl-gard grading cap.'s on P3-4 and P3-5. If necessary, the isolation can be moved back to UT1D-345 for the second week. |
| 6971 | PAS APPROUVÉ | 25 juin, 2012 AD | 28 juin, 2012 AD | Relay Dept.; Permit required to install four additional L1134 A&B Protection Tones (one Permissive and one Direct Trip for each A&B) between Mactaquac and Keswick. |
| 4622 | PAS APPROUVÉ | 25 juin, 2012 AD | 29 juin, 2012 AD | work permit on L2145 (while Salisbury T1 is being overhauled) to replace poles on str. 75 (5 pole dead end), and insulators in 230 kV yard |
| 7144 | PAS APPROUVÉ | 25 juin, 2012 AD | 27 juin, 2012 AD | work permit to replace seized bearings in 28-01LD, discussed with G Falls Plant staff, Hydro Planning contacted |
| 6714 | PAS APPROUVÉ | 3 juillet, 2012 AD | 7 juillet, 2012 AD | HVEM's; will be requesting an In-Plant O&M 50 Permit to perform the six year overhaul on transformer TU1. |
| 6941 | PAS APPROUVÉ | 4 juillet, 2012 AD | 6 juillet, 2012 AD | HVEM's; permit to doble test the L1212 PT's at Norton. There will be another Permit applied for, to paint the L1212 D.E. structure in Sub#2, that was not completed in 2011. |
| 4729 | PAS APPROUVÉ | 9 juillet, 2012 AD | 13 juillet, 2012 AD | HVEM's; perform 15 year overhaul on breaker E2104-TC3. |
| 4735 | PAS APPROUVÉ | 9 juillet, 2012 AD | 20 juillet, 2012 AD | HVEM's; perform 6 year T1 overhaul, and replace PT grounding cubicle (Capital Job). |
| 4601 | PAS APPROUVÉ | 16 juillet, 2012 AD | 3 août, 2012 AD | HVEM's; perform 6 year overhaul on Moncton T1 transformer, T1-138 6 year maintenance, T1-C replacement, and replace PT grounding cubicle (Capital job) |
| 6586 | PAS APPROUVÉ | 16 juillet, 2012 AD | 20 juillet, 2012 AD | HVEM's; permit required to perform the 12 year overhaul on breaker E2102-TC1. |
| 7016 | PAS APPROUVÉ | 16 juillet, 2012 AD | 16 juillet, 2012 AD | hold off Bus 37 to service switch 7B35 (with breaker CO3-7 open) - the other switch was serviced the previous year |
| 4722 | PAS APPROUVÉ | 23 juillet, 2012 AD | 26 juillet, 2012 AD | HVEM's; replace Bathurst L2103 PT's (3), Capital Job. |
| 6716 | PAS APPROUVÉ | 30 juillet, 2012 AD | 10 août, 2012 AD | HVEM's; permit required to perform the six year overhaul of the T4 transformer, perform an internal inspection, and change the oil. |
| 6384 | PAS APPROUVÉ | 7 août, 2012 AD | 10 août, 2012 AD | HVEM's; replace Marysville L1112 PT's (3). |
| 7071 | PAS APPROUVÉ | 7 août, 2012 AD | 9 août, 2012 AD | HVEM's; permit required to perform 6 year maintenance on CO3-8, and apply syl-gard to breaker. |
| 4723 | PAS APPROUVÉ | 13 août, 2012 AD | 31 août, 2012 AD | HVEM's; perform 6 year overhaul on T1 transformer, replace T1 oil, and replace PT grounding cubicle (Capital Job). Also, maintenance on breakers T1-11, T1-12, T1-13, and T1-14, and overhaul transformer SS1. |
| 4718 | PAS APPROUVÉ | 13 août, 2012 AD | 17 août, 2012 AD | HVEM's; replace L1104 PT's (3) and perform six year maintenance on breaker F1104 at Marysville Terminal. |
| 4719 | PAS APPROUVÉ | 13 août, 2012 AD | 17 août, 2012 AD | HVEM's; perform 12 year overhaul on breaker SA3-1. |
| 4730 | ANNULÉ | 20 août, 2012 AD | 24 août, 2012 AD | HVEM's; perform 15 year overhaul on breaker ETC3. |
| 6932 | PAS APPROUVÉ | 20 août, 2012 AD | 31 août, 2012 AD | HVEM's; Permit required to perform a six year overhaul on TU3, re-gasket, and change oil. Bayside Outage starts August 17, approx. 40 days. |
| 6783 | PAS APPROUVÉ | 20 août, 2012 AD | 24 août, 2012 AD | HVEM's; perform the six year overhaul on transformer TU1, during the planned Generation outage. |
| 7124 | PAS APPROUVÉ | 20 août, 2012 AD | 20 août, 2012 AD | work permit to service switch 3013-010 |
| 7125 | PAS APPROUVÉ | 20 août, 2012 AD | 20 août, 2012 AD | work permit to service switch NO3013D and G3013-4200 |
| 6718 | PAS APPROUVÉ | 27 août, 2012 AD | 31 août, 2012 AD | HVEM's; perform six year overhaul and replace oil in transformer T3, perform maintenance on breakers G6 and G7, and maintenance on switch 4290-S003. |
| 4731 | PAS APPROUVÉ | 27 août, 2012 AD | 31 août, 2012 AD | HVEM's; perform 15 year overhaul on breaker E2103-TC4. |
| 6596 | PAS APPROUVÉ | 27 août, 2012 AD | 31 août, 2012 AD | HVEM's; permit required to perform the following work...replace one Bus 1 PT, breaker T1 six year maintenance, switcher TSB1-B2 six year maintenance, switcher 88-CD six year maintenance, Doble L0088 and L0089 metering units, and Doble the C88 PT. |
| 6587 | PAS APPROUVÉ | 4 septembre, 2012 AD | 8 septembre, 2012 AD | HVEM's; permit required to perform the 12 year overhaul on breaker ETC2. |
| 6717 | PAS APPROUVÉ | 4 septembre, 2012 AD | 23 septembre, 2012 AD | HVEM's; perform the six year overhaul, inhibit oil, replace bushings on T1 transformer. Repair hot spot on breaker MT-01. |
| 5865 | PAS APPROUVÉ | 10 septembre, 2012 AD | 16 septembre, 2012 AD | Annual maintenance |
| 7140 | PAS APPROUVÉ | 10 septembre, 2012 AD | 11 septembre, 2012 AD | hold off L1142 to service ME1142D, Billy will ask to open switch (second day is rain day) |
| 5866 | PAS APPROUVÉ | 17 septembre, 2012 AD | 21 septembre, 2012 AD | Annual maintenance |
| 4733 | PAS APPROUVÉ | 24 septembre, 2012 AD | 28 septembre, 2012 AD | HVEM's; permit to perform 6 year overhaul on T6. |
| 4688 | PAS APPROUVÉ | 24 septembre, 2012 AD | 28 septembre, 2012 AD | HVEM's; perform 6 year overhaul on T1 transformer. |
| 6561 | ANNULÉ | 29 septembre, 2012 AD | 2 octobre, 2012 AD | MPRP |
| 4720 | ANNULÉ | 1 octobre, 2012 AD | 5 octobre, 2012 AD | HVEM's; perform 12 year overhaul on breaker SA3-2. |
| 4732 | ANNULÉ | 1 octobre, 2012 AD | 5 octobre, 2012 AD | HVEM's; perform 15 year overhaul on breaker ETC4. |
| 6504 | PAS APPROUVÉ | 16 octobre, 2012 AD | 19 octobre, 2012 AD | HVEM's; permit required to replace the three L2131 PT's. TLM switch maintenance. |
| 6562 | PAS APPROUVÉ | 23 octobre, 2012 AD | 30 octobre, 2012 AD | MPRP |
| 6786 | PAS APPROUVÉ | 7 novembre, 2012 AS | 7 novembre, 2012 AS | HVEM's; perform the 3 year maintenance on breaker U4-1134. |
| 6811 | PAS APPROUVÉ | 8 novembre, 2012 AS | 22 novembre, 2012 AS | Fall outage |
| 6787 | PAS APPROUVÉ | 8 novembre, 2012 AS | 8 novembre, 2012 AS | HVEM's; perform 3 year maintenance on breaker U6-B2. |
|